PMI Scheduling Professional PMI-SP Question # 16 Topic 2 Discussion

PMI Scheduling Professional PMI-SP Question # 16 Topic 2 Discussion

PMI-SP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?


A.

Precedence Diagramming Method


B.

Schedule network template


C.

Dependency determination


D.

Activity on the Node


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.