PMI Scheduling Professional PMI-SP Question # 82 Topic 9 Discussion

PMI Scheduling Professional PMI-SP Question # 82 Topic 9 Discussion

PMI-SP Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?


A.

Scope baseline


B.

Activity attributes


C.

Activity list


D.

Activity resource requirements


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.