Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

PMI-SP Question 81

Based on the network diagram, find out which path is the critical path for this project?


A.

ABEHJ


B.

ABDIJ


C.

ABDHJ


D.

ACFIJ