You are the project manager for GGY Project. You are working with your project team to record the actual durations for the activities they have completed in the project schedule. Mary, one of your project team members, wants to know why you need to know how long it actually took the project team to complete their assignments as long as the project work is completed. Which of the following is the best response for Mary's query?


A.

Actual durations need to be recorded to track process improvement.


B.

Actual durations need to be recorded to create the schedule baseline.


C.

Actual durations need to be recorded to measure the actual progress of the project.


D.

Actual durations need to be recorded to perform quality control on the project management processes.