Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 6 out of 7 pages
Viewing questions 51-60 out of questions
Questions # 51:

A financial service firm adheres to heavily regulated compliance legislation. During the firm's latest project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-based approach. This approach ensured compliance with the legislative requirements for properly storing confidential employee salary information. The risk manager recorded this information in the project's risk management plan.

What is the organization's risk maturity level?

Options:

A.

No maturity


B.

Low maturity


C.

Medium maturity


D.

High maturity


Expert Solution
Questions # 52:

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.

Issue log


B.

Change log


C.

Assumption log


D.

Risk-adjusted back log


Expert Solution
Questions # 53:

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

Options:

A.

Close the risks and update their status in the risk register.


B.

Use their contingency with other risks that are still open.


C.

Remove the risk from the list as they are no longer applicable.


D.

Reevaluate those risks' severity, and update the risk register.


Expert Solution
Questions # 54:

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

Options:

A.

Updated probability and impact matrix


B.

Updated risk register


C.

Updated mitigation plans


D.

Updated project schedule 


Expert Solution
Questions # 55:

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Options:

A.

Scope of work and requirements


B.

Monte Carlo analysis from a similar project


C.

List of pre-approved contractors


D.

Organization chart for city permit department


E.

Risk management plan


Expert Solution
Questions # 56:

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.

Conduct a subject matter expert (SME) meeting.


B.

Perform qualitative analysis.


C.

Prioritize after quantitative analysis


D.

Prioritize the stakeholders affected.


Expert Solution
Questions # 57:

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

Options:

A.

Mitigate


B.

Accept


C.

Enhance


D.

Exploit


Expert Solution
Questions # 58:

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

Options:

A.

Time Series Analysis


B.

Regression Analysis


C.

Variance Analysis


D.

Monte Carlo Analysis 


Expert Solution
Questions # 59:

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

Options:

A.

Probability of a response triggering a secondary risk


B.

How the response will affect the quality of the components


C.

If the risk response is tied to an activity on the critical path


D.

Verify due dates for the actions have been identified


Expert Solution
Questions # 60:

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

Options:

A.

Verify whether or not any identified risks might occur and implement the risk response plan.


B.

Regularly check and report on the status of risks identified according to their prioritization.


C.

Monitor the status and oversee execution of the risk response plan for each identified risk.


D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.


E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.


Expert Solution
Viewing page 6 out of 7 pages
Viewing questions 51-60 out of questions