Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 3 out of 7 pages
Viewing questions 21-30 out of questions
Questions # 21:

A project manager has requested the risk manager's support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.

What should the risk manager recommend?

Options:

A.

The new component should be purchased.


B.

Both options are losses to the project.


C.

Cost to expedite the execution is not worth the added risk.


D.

Perform a Monte Carlo simul-ation to quantify the impacts.


Expert Solution
Questions # 22:

A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization's project risk baseline.

What should the risk manager do?

Options:

A.

Prioritize the risk management plan.


B.

Arrange the risk mitigation plan.


C.

Create a risk action plan with risk owners.


D.

Prioritize the risk register.


Expert Solution
Questions # 23:

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.


B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.


C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.


D.

Add the identified risk to the risk register for future probability and impact analysis.


Expert Solution
Questions # 24:

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.

Product Manager


B.

Risk Action Owner


C.

Risk Owner


D.

Project Manager


Expert Solution
Questions # 25:

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.

Perform a qualitative risk analysis and update the results.


B.

Update the assumptions/exclusions register with the new information.


C.

Update the risk register and prepare for the Monte Carlo analysis.


D.

Perform a quantitative risk analysis and update the results.


Expert Solution
Questions # 26:

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.


B.

Inform the sponsor that these risks should be added according to experience.


C.

Add the risks to the risk register and determine a contingency.


D.

Discuss and evaluate the identified risks with the project team.


Expert Solution
Questions # 27:

In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers

this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about

to drop their intention to continue executing the project. The risk manager does not understand their decision.

What should the risk manager do next to understand the major stakeholder's decision regarding the project?

Options:

A.

Perform a risk impact analysis.


B.

Perform a risk reserve analysis.


C.

Perform a procurement analysis.


D.

Perform a stakeholder impact and influence analysis.


Expert Solution
Questions # 28:

A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.

What should the risk manager do to prevent this from happening again?

Options:

A.

Document the risks and response actions in a clear manner.


B.

Communicate with the project manager on the topic.


C.

Assign owners who will be fully accountable to managing the risks.


D.

Define the response plans and take the lead in implementing them.


Expert Solution
Questions # 29:

As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.

What additional information should the risk manager prioritize in the risk register updates?

Options:

A.

Actual outcomes and performance of risk management strategies


B.

Actual outcomes of the project's risks and risk responses


C.

Actual costs and schedule delays of risk events


D.

Actual cost impact of risk events


Expert Solution
Questions # 30:

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

Options:

A.

Detailed work breakdown structure (WBS)


B.

Lessons learned from previous projects


C.

Baselines approved by the project team


D.

Actual data from the current project


Expert Solution
Viewing page 3 out of 7 pages
Viewing questions 21-30 out of questions