Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 7 out of 7 pages
Viewing questions 61-70 out of questions
Questions # 61:

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Options:

A.

Create a new project plan including the new risks.


B.

Review the effectiveness of the risk process.


C.

Update the risk management plan.


D.

Escalate the project risks to upper management. 


Expert Solution
Questions # 62:

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

Options:

A.

Put the risk on the watch list.


B.

Seek guidance from subject matter experts (SMEs).


C.

Ignore this risk as it is not critical.


D.

Inform the stakeholders about this risk.


Expert Solution
Questions # 63:

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded


B.

When the stakeholders agree a risk is no longer applicable


C.

When the risk has been realized and can no longer happen again


D.

When iterative data analysis determines the risk is not applicable


Expert Solution
Questions # 64:

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.


B.

Provide a numerical estimate of the overall effect of risk on the objectives.


C.

Track identified risks and maintain the viability of response plans.


D.

Develop the overall risk management strategy for risk integration. 


Expert Solution
Questions # 65:

A risk manager is preparing the risk strategy for a strategic project, which involves stakeholders based in multiple locations. What should the risk manager do at this stage?

Options:

A.

Update the risk communications plan to include all stakeholders.


B.

Define the risk processes and tools to be adopted.


C.

Update the risk register to include this stakeholder-related risk.


D.

Refine the risk assumptions and criteria to be used.


Expert Solution
Questions # 66:

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project


B.

By helping to determine the overall project risks


C.

By helping the lessons learned from previous risks to be efficiently utilized


D.

By helping to update the project scope statement document


E.

By helping update the risk register and close out expired risks 


Expert Solution
Questions # 67:

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Options:

A.

Execute the security risks contingency plan.


B.

Get a report of customers affected by the risk.


C.

Identify residual and secondary risks.


D.

Coordinate a response with the risk owner.


Expert Solution
Questions # 68:

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

Options:

A.

Revisit this risk in the risk register and redefine the mitigation strategy.


B.

Activate the contingency plan to handle this risk during execution.


C.

Mark this new risk as an extremely high priority and inform all stakeholders.


D.

Ask the project sponsor for more budget to deal with this risk.


Expert Solution
Questions # 69:

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.


B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.


C.

Assess and record associated secondary risks and proceed to treat them as any other risks.


D.

Proceed with the project as normal since a minor number of residents will be effected negatively.


Expert Solution
Viewing page 7 out of 7 pages
Viewing questions 61-70 out of questions