Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 4 out of 7 pages
Viewing questions 31-40 out of questions
Questions # 31:

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Options:

A.

Scenario-based risk analysis


B.

Quantitative risk analysis


C.

Qualitative risk analysis


D.

Monte Carlo analysis 


Expert Solution
Questions # 32:

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

Options:

A.

Update the project management plan to add contingency.


B.

Perform an assumptions and constraints analysis.


C.

Complete an assessment and confirm the response with the sponsors.


D.

Implement mitigation measures for those risks.


Expert Solution
Questions # 33:

A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

Options:

A.

Evaluating the project's probability of success


B.

Identifying threats and opportunities


C.

Evaluating the project's impact


D.

Performing a qualitative analysis


Expert Solution
Questions # 34:

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.


B.

Assess and modify the project risk management plan in response to the new directive.


C.

Accept project risks since it is already within the enterprise-wide threshold.


D.

Advise that the decision could increase the risk of their portfolio exponentially.


Expert Solution
Questions # 35:

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.

Risk burndown chart


B.

Ishikawa diagram


C.

Risk breakdown structure (RBS)


D.

Affinity diagram


Expert Solution
Questions # 36:

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.


B.

Advise the client that the project has exhausted contingency.


C.

Quantify the risk exposure that exceeds project contingency.


D.

Generate reports to assess and communicate the project risk level.


Expert Solution
Questions # 37:

The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.

What should the risk manager do?

Options:

A.

Create a list of potential issues.


B.

Consult the project management plan.


C.

Conduct risk management exercises.


D.

Perform qualitative risk analysis.


Expert Solution
Questions # 38:

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.

Evaluate any new risks that are introduced due to the change in scope.


B.

Update the risk management plan to reflect the scope change.


C.

Reassess the identified risks that impact the project scope.


D.

Update the risk register to identify, analyze, and plan a response for any new risk.


Expert Solution
Questions # 39:

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.

Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options:

A.

Work with the project team to conduct a decision tree analysis for each risk or set of related risks.


B.

Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and defend project reserves.


C.

Conduct a Monte Carlo simul-ation to understand the probabilities of various risk outcomes.


D.

Use the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure project reserves are adequate to cover this amount.


E.

Focus attention and resources on identified risks with the highest potential to impact the project.


Expert Solution
Questions # 40:

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Options:

A.

Engage with the team to present the actual results to the sponsor.


B.

Prepare a management of change (MOC) to adjust the project cost and duration.


C.

Move forward with the lessons learned from the sprint.


D.

Review the assumptions to understand any change.


Expert Solution
Viewing page 4 out of 7 pages
Viewing questions 31-40 out of questions