Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 2 out of 7 pages
Viewing questions 11-20 out of questions
Questions # 11:

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

Options:

A.

Risk management plan


B.

Clients' credit scores


C.

Organization's mission and vision


D.

Historical data from the credit portfolio


Expert Solution
Questions # 12:

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

Options:

A.

Risks are documented to the practicable extent possible.


B.

Probability of the risk was very low. so the risk was not documented.


C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.


D.

A similar risk never occurred in the past, so it was not considered. 


Expert Solution
Questions # 13:

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Options:

A.

Residual risk


B.

Primary risk


C.

Secondary risk


D.

Normal risk


Expert Solution
Questions # 14:

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis


B.

Conduct a sensitivity analysis


C.

Perform a decision tree analysis


D.

Conduct an analytic hierarchy process


Expert Solution
Questions # 15:

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.

Avoid the risk


B.

Transfer the risk


C.

Ignore the risk


D.

Accept the risk


Expert Solution
Questions # 16:

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

Options:

A.

Review and revise the strategies periodically.


B.

Implement the strategies after completing the risk analysis.


C.

Implement the strategies immediately.


D.

Ensure the strategies are approved by the stakeholders.


Expert Solution
Questions # 17:

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts


B.

Conduct a checklist analysis on each risk


C.

Create a risk response plan for those risks


D.

Review the risk register to check for the new risks


Expert Solution
Questions # 18:

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

Options:

A.

Confirm the risk triggers are still valid.


B.

Ask the architect to develop acceptance criteria.


C.

Review the feature with the project team.


D.

Escalate the issue to the project board.


Expert Solution
Questions # 19:

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis


B.

Delphi technique


C.

Decision tree analysis


D.

Probability impact matrix


Expert Solution
Questions # 20:

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.

A potential need to share the space with other machinery


B.

A different type of equipment received before installation


C.

A time delay during air conditioning installation activities


D.

A quality nonconformance issue raised during the inspection


Expert Solution
Viewing page 2 out of 7 pages
Viewing questions 11-20 out of questions