Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 5 out of 7 pages
Viewing questions 41-50 out of questions
Questions # 41:

An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.


B.

Clarify project goals and project contract constraints.


C.

Promote cross-training and mentoring among team members.


D.

Develop a reward system related to position and years of experience.


Expert Solution
Questions # 42:

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

Options:

A.

Perform a probability and impact assessment


B.

Perform Monte Carlo simul-ations


C.

Perform a sensitivity analysis


D.

Perform a risk data quality assessment


Expert Solution
Questions # 43:

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

Options:

A.

Include the risk in the register and communicate with the stakeholders.


B.

Communicate with the client to provide the previous shutdown plan.


C.

Review and update the project schedule.


D.

Interview the other project manager to learn more details.


Expert Solution
Questions # 44:

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Options:

A.

Provided regular training to the risk owners for plan implementation


B.

Determined risk triggers and thresholds in the risk response plan


C.

Increased communications to influence stakeholder risk responses


D.

Updated the project schedule, adding risk owner implementation tasks.


Expert Solution
Questions # 45:

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?

Options:

A.

Agree with the external supplier on the timeline.


B.

Register the risk with a medium impact.


C.

Align with stakeholders on the risk threshold.


D.

Engage another supplier with shorter delivery times.


Expert Solution
Questions # 46:

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

Options:

A.

Ask the sponsor to define the risk strategy to align with client needs.


B.

Develop a framework and engage the team in creating a risk plan.


C.

Train the team on basic techniques and defer the risk strategy for later.


D.

Concentrate on high-priority risks to meet the sponsor's expectations.


Expert Solution
Questions # 47:

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?

Options:

A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.


B.

Refer to the project charter to find guidelines and stakeholder communication channels.


C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.


D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.


Expert Solution
Questions # 48:

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.

Earned value management (EVM) variance metrics


B.

A risk burndown chart showing remaining risks


C.

The format established in the risk management plan


D.

An itemized list of remaining risks and their scores 


Expert Solution
Questions # 49:

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X's project manager avoid this situation in the future?

Options:

A.

Prepare a contingency response plan to implement when delays occur


B.

Ask the other project manager to officially confirm the new date in writing


C.

Request that the other project manager be added to relevant reports


D.

Request that the other project manager inform if any additional delays are expected


Expert Solution
Questions # 50:

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned


B.

Contingency register


C.

Risk register


D.

Issue log


Expert Solution
Viewing page 5 out of 7 pages
Viewing questions 41-50 out of questions