Questions # 71:

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.


B.

Communicate to the stakeholders about the updated timeline.


C.

Ask the development team to fast-track upcoming activities.


D.

Add two resources so the critical activities will finish on time.


Expert Solution
Questions # 72:

Which of the following best describes the role of a PM for a CRM system?

Options:

A.

To track sales


B.

To store customer information


C.

To implement new features


D.

To pay vendors


Expert Solution
Questions # 73:

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

Options:

A.

Regression testing


B.

Smoke testing


C.

Stress testing


D.

Automation testing


Expert Solution
Questions # 74:

Which of the following is a Kanban concept?

Options:

A.

Ensuring business alignment by development iteration


B.

Representing cost-effective tasks through different colors


C.

Allocating resources to high-priority tasks


D.

Managing flow by limiting work in progress


Expert Solution
Questions # 75:

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project's budget during the execution phase?

Options:

A.

Evaluate the project's communication plan.


B.

Track and manage the project’s financial condition.


C.

Report the project’s risks and issues.


D.

Distribute resources to the project.


Expert Solution
Questions # 76:

During schedule planning, a project manager determined the logical dependencies required to complete the project. Which of the following activities should the project manager do next?

Options:

A.

Determine the stakeholders positively impacted in the project.


B.

Determine the escalation reporting tool to be used in the project.


C.

Determine the resources required to complete the tasks.


D.

Determine the total cost incurred in the project's execution.


Expert Solution
Questions # 77:

Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

Options:

A.

Social


B.

Regulatory


C.

Environmental


D.

Governmental


Expert Solution
Questions # 78:

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

Options:

A.

negotiating resources.


B.

assigning resources.


C.

assessing the resource pool.


D.

adding resources to the schedule.


Expert Solution
Questions # 79:

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

Options:

A.

Status


B.

Focus


C.

Brainstorming


D.

Informative


Expert Solution
Questions # 80:

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.


B.

A project manager did not release the resources


C.

A project manager did not remove the system access.


D.

A project manager did not provide the project sign-off.