Questions # 61:

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

Options:

A.

Create a list of tasks and share it with the team.


B.

Resend the scope of work to the team.


C.

Review the Gantt chart weekly with the team.


D.

Have the project sponsor meet with the team.


Expert Solution
Questions # 62:

Which of the following best describes a program in the context of project management?

Options:

A.

It is a group of unrelated projects within an organization


B.

It is used to represent the daily activities of multiple projects


C.

It is a consolidation of related projects with a common goal


D.

It provides the definition of a project workload


Expert Solution
Questions # 63:

Which of the following can be inferred?

Options:

A.

The project will be completed on time.


B.

Task D must be reworked.


C.

Task B needs to be finished before task C starts.


D.

The project is over budget and behind schedule.


Expert Solution
Questions # 64:

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

Options:

A.

Percentage of controls with identified business owners


B.

Percentage of risk investments with defined business cases


C.

Ratio of control cost to operational budget


D.

Senior management satisfaction scores related to the security program


Expert Solution
Questions # 65:

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

Options:

A.

Start-to-finish


B.

Finish-to-finish


C.

Finish-to-start


D.

Start-to-start


Expert Solution
Questions # 66:

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.


B.

Capture lessons learned.


C.

Document historical information.


D.

Release resources.


Expert Solution
Questions # 67:

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

Options:

A.

Change the precedence of the tasks to " finish-to-start " .


B.

Evaluate and modify the schedule with a burndown chart


C.

Assign additional resources to prevent overwork.


D.

Perform critical path analysis


Expert Solution
Questions # 68:

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

Options:

A.

Transfer


B.

Avoid


C.

Accept


D.

Mitigate


Expert Solution
Questions # 69:

The executive leadership of an agile company has launched a new strategy. This new strategy impacts new features that are in development with the project team. Which of the following describes what the team should do next?

Options:

A.

Resource loading


B.

Analyzing the critical path


C.

Prioritizing backlog


D.

Determining contingency reserves


Expert Solution
Questions # 70:

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

Options:

A.

Defect log


B.

Change log


C.

Issue log


D.

Risk log


Expert Solution