Questions # 61:

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

Options:

A.

Informal communication


B.

Formal communication


C.

Synchronous communication


D.

Asynchronous communication


Expert Solution
Questions # 62:

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

Options:

A.

Status report


B.

Issue log


C.

Risk report


D.

Risk register


Expert Solution
Questions # 63:

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

Options:

A.

Service-level agreement


B.

Functional testing


C.

Warranty period


D.

Audit


Expert Solution
Questions # 64:

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Options:

A.

Creating a backlog


B.

Managing the quality of deliverables


C.

Updating the issue log


D.

Performing a risk assessment


E.

Validating the deliverables


F.

Reconciling the project budget


Expert Solution
Questions # 65:

Which of the following BEST identifies the intent and purpose of a project closeout report?

Options:

A.

To provide documentation of lessons learned


B.

To document variances from the initial project baseline


C.

To validate that a project has been successfully completed


D.

To release resources and terminate all access rights


Expert Solution
Questions # 66:

Which of the following is a consideration when determining a project's ESG factors?

Options:

A.

Project management methodology


B.

IT infrastructure security


C.

Proper accounting practices


D.

Corporate values compliance


Expert Solution
Questions # 67:

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined.


B.

There is a non-disclosure agreement in place.


C.

There are multiple requirements for the product.


D.

The PM wants to simplify the logistics of the required product.


Expert Solution
Questions # 68:

Which of the following requires the MOST availability from the business team?

Options:

A.

SDLC


B.

Scrum


C.

PRINCE2


D.

Waterfall


Expert Solution
Questions # 69:

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

Options:

A.

Change log


B.

Project Gantt


C.

Issue log


D.

Requirements traceability matrix


Expert Solution
Questions # 70:

A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?

Options:

A.

Planning


B.

Closure


C.

Initiation


D.

Execution