Questions # 61:

During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

Options:

A.

Awareness of the local environment


B.

Awareness of the brand value


C.

Awareness of the resource constraints


D.

Awareness of the company's mission


Expert Solution
Questions # 62:

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

Options:

A.

Work breakdown structure


B.

Change log


C.

Project success criteria


D.

Milestone chart


Expert Solution
Questions # 63:

Which of the following can be inferred?

Options:

A.

The project will be completed on time.


B.

Task D must be reworked.


C.

Task B needs to be finished before task C starts.


D.

The project is over budget and behind schedule.


Expert Solution
Questions # 64:

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

Options:

A.

Update the risk register.


B.

Escalate the issue for exceptional approval.


C.

Communicate to the stakeholders.


D.

Submit a duplicate change request.


Expert Solution
Questions # 65:

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options:

A.

Escalate to vendor management.


B.

Consult the request for proposal.


C.

Review the meeting cadence.


D.

Reinforce the rules of engagement.


Expert Solution
Questions # 66:

A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

Options:

A.

Consult with the legal department.


B.

Update the issue log.


C.

Start a new RFP immediately.


D.

Perform a PERT analysis.


Expert Solution
Questions # 67:

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning


B.

Initiating


C.

Controlling


D.

Executing


Expert Solution
Questions # 68:

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

Options:

A.

Scatter diagram


B.

Decision tree


C.

Pareto chart


D.

Histogram


Expert Solution
Questions # 69:

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

Options:

A.

Removing access


B.

Closing contracts


C.

Project sign-off


D.

Project evaluation


Expert Solution
Questions # 70:

Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?

Options:

A.

Project communication plan


B.

Project management plan


C.

Project business case


D.

Project schedule