CompTIA Project+ Certification (2025) PK0-005 Question # 63 Topic 7 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 63 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

Given the following velocity chart:

PK0-005 Question 63

Which of the following updates on the project status should the Scrum master provide to the senior management team?


A.

The project utilized all of its available reserve.


B.

The project has scope creep.


C.

The project deviated from the critical path.


D.

The project is trending ahead of schedule.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.