A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
A finish-to-start dependency is a type of relationship dependency in project management, where the start of one task depends on the finish of another task12. In this case, the project manager is using a finish-to-start dependency, because testing cannot start until requirements development is finished. This implies that testing is a successor task, and requirements development is a predecessor task. A finish-to-start dependency is the most common type of dependency in project management, and it ensures that tasks are performed in a logical sequence34. References = CompTIA Project+ Certification Study Guide5, CompTIA Project+ Certification Exam Objectives6, Understanding Dependencies in Project Management [2023] • Asana1, Dependencies in Project Management | Smartsheet2, Understanding Task Dependencies in Project Management3, What are Dependencies in Project Management? - KnowledgeHut4
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit