Questions # 81:

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

Options:

A.

Business collaboration tool


B.

Email


C.

Virtual meetings


D.

Enterprise CMS


Expert Solution
Questions # 82:

Which of the following offers administrators more direct control over operating systems?

Options:

A.

Infrastructure as a service


B.

Software as a service


C.

Functions as a service


D.

Platform as a service


Expert Solution
Questions # 83:

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

Options:

A.

Shared folder


B.

Infrastructure


C.

Multitiered architecture


D.

Data warehouse


Expert Solution
Questions # 84:

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project ' s closure. Which of the following would have most likely prevented the data from being stolen?

Options:

A.

Removing access


B.

Closing contracts


C.

Project sign-off


D.

Project evaluation


Expert Solution
Questions # 85:

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

Options:

A.

Project status report


B.

Project evaluation review


C.

Project management software


D.

Requirements traceability matrix


Expert Solution
Questions # 86:

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

Options:

A.

Transfer


B.

Mitigate


C.

Avoid


D.

Accept


Expert Solution
Questions # 87:

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

Options:

A.

Forming, storming, performing, norming, adjourning


B.

Forming, performing, storming, norming, adjourning


C.

Forming, norming, storming, performing, adjourning


D.

Forming, storming, norming, performing, adjourning


Expert Solution
Questions # 88:

Which of the following would be considered operational security?

Options:

A.

Mobile device compliance


B.

Background screening


C.

Multifactor authentication


D.

Facility access


Expert Solution
Questions # 89:

During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?

Options:

A.

Milestone chart


B.

Velocity chart


C.

Task board


D.

Burndown chart


Expert Solution
Questions # 90:

A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?

Options:

A.

Seek approval before continuing


B.

Edit the requirements document


C.

Disregard the update


D.

Notify the users of the new features


Expert Solution