Questions # 81:

Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

Options:

A.

Assign action items to attendees.


B.

Distribute an agenda.


C.

Email the minutes from the previous meeting.


D.

Schedule a convenient time.


Expert Solution
Questions # 82:

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

Options:

A.

Key stakeholder identification


B.

Preliminary procurement


C.

Solution design determination


D.

Critical factor enlistment


Expert Solution
Questions # 83:

A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?

Options:

A.

Risk assessment


B.

Preliminary scope statement


C.

Work breakdown structure


D.

Milestone chart


Expert Solution
Questions # 84:

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

Options:

A.

The project closeout report


B.

A handover to operations


C.

Phase-gate review documentation


D.

A transition plan


Expert Solution
Questions # 85:

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

Options:

A.

Milestone chart


B.

Work breakdown structure


C.

Project charter


D.

Detailed scope statement


Expert Solution
Questions # 86:

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.

Kanban board


B.

Pareto chart


C.

Ishikawa diagram


D.

Decision tree


Expert Solution
Questions # 87:

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Question # 87

Which of the following is the current status of the process?

Options:

A.

Based on the rule of seven, the process is under control


B.

The amount of data is insufficient to determine if quality is low.


C.

The process is out of control and should be revised.


D.

The goal should be adjusted since most of the data points are close to the lower limit.


Expert Solution
Questions # 88:

The project manager must create a project charter. Which of the following should be included in the charter?

Options:

A.

Project schedule


B.

Resource allocation


C.

Risk plan


D.

Stakeholder identification


Expert Solution
Questions # 89:

A company is starting a new implementation project The stakeholders are reviewing RFP responses to help make a decision about which project management consulting firm to hire. Given the following information:

Question # 89

Which of the following is the best consulting firm for the company to hire?

Options:

A.

Consulting firm 1


B.

Consulting firm 2


C.

Consulting firm 3


D.

Consulting firm 4


Expert Solution
Questions # 90:

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

Options:

A.

Data plan


B.

Contingency plan


C.

Rollback plan


D.

Recovery plan


Expert Solution