PK0-005 Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?


A.

Update the issue log.


B.

Apply the contingency plan.


C.

Transfer the risk.


D.

Submit a change request.