Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

CompTIA Project+ Certification (2026) PK0-005 Question # 115 Topic 12 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 115 Topic 12 Discussion

PK0-005 Exam Topic 12 Question 115 Discussion:
Question #: 115
Topic #: 12

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?


A.

Hold a new backlog prioritization meeting.


B.

Add milestones to check the project ' s progress.


C.

Adjust the task relationship to complete coding in advance.


D.

Apply contingency buffers to the critical path.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.