PK0-005 Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?


A.

The project utilized all of its available reserve.


B.

The project has scope creep.


C.

The project deviated from the critical path.


D.

The project is trending ahead of schedule.