New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 47 Topic 5 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 47 Topic 5 Discussion

PK0-005 Exam Topic 5 Question 47 Discussion:
Question #: 47
Topic #: 5

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?


A.

Memorandum of understanding


B.

Request for information


C.

Statement of work


D.

Non-disclosure agreement


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.