PK0-005 Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?


A.

Defect log


B.

Change log


C.

Issue log


D.

Risk log


Get Premium PK0-005 Questions