New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 48 Topic 5 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 48 Topic 5 Discussion

PK0-005 Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?


A.

Avoiding


B.

Smoothing


C.

Forcing


D.

Compromising


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.