Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2026) PK0-005 Question # 120 Topic 13 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 120 Topic 13 Discussion

PK0-005 Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

A software development team implemented an approved change but does not obtain the expected results. The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?


A.

Scope creep


B.

Recovery plan


C.

Incident report


D.

Risk response


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.