CompTIA Project+ Certification (2025) PK0-005 Question # 33 Topic 4 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 33 Topic 4 Discussion

PK0-005 Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?


A.

Request a change control ticket.


B.

Review the schedule plan.


C.

Refine the project documentation.


D.

Revise the communication plan.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.