CompTIA Project+ Certification (2025) PK0-005 Question # 90 Topic 10 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 90 Topic 10 Discussion

PK0-005 Exam Topic 10 Question 90 Discussion:
Question #: 90
Topic #: 10

Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:

PK0-005 Question 90

Which of the following best describes the team's performance?


A.

The team needs to adjust the planned work based on results.


B.

The team’s velocity is getting better.


C.

The team understands its velocity and is planning in an accurate manner.


D.

The team is doing more work than planned.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.