Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

CompTIA Project+ Certification (2026) PK0-005 Question # 92 Topic 10 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 92 Topic 10 Discussion

PK0-005 Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?


A.

Build


B.

Subscription


C.

Lease


D.

Buy


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.