CompTIA Project+ Certification (2025) PK0-005 Question # 91 Topic 10 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 91 Topic 10 Discussion

PK0-005 Exam Topic 10 Question 91 Discussion:
Question #: 91
Topic #: 10

Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?


A.

Project communication plan


B.

Project management plan


C.

Project business case


D.

Project schedule