Question #: 91
Topic #: 10

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?


A.

Validate the scope.


B.

Create the work breakdown structure.


C.

Define the scope.


D.

Collect the requirements.