Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the CompTIA Project+ PK0-005 Questions and answers with CertsForce

Viewing page 5 out of 14 pages
Viewing questions 41-50 out of questions
Questions # 41:

Which of the following tasks should the project manager complete first when validating deliverables?

Options:

A.

Assess the documentation.


B.

Obtain stakeholder feedback.


C.

Review the project objectives.


D.

Mitigate risks.


Expert Solution
Questions # 42:

Which of the following provides a layered approach to logging in to systems that contain an organization ' s most valuable intellectual property?

Options:

A.

Remote access


B.

Password protection


C.

Multifactor authentication


D.

Virtual private network


Expert Solution
Questions # 43:

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Options:

A.

Review the detailed plan.


B.

Develop a preliminary scope.


C.

Develop a transition plan.


D.

Develop a project management plan.


E.

Review the resource pool.


F.

Review the project objectives.


Expert Solution
Questions # 44:

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options:

A.

Determine budget constraints.


B.

Validate the business case.


C.

Update the project charter.


D.

Create a project schedule


Expert Solution
Questions # 45:

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization ' s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

Options:

A.

Train users on the proper use of the system.


B.

Escalate the issue to the CCB


C.

Hold sessions to understand user challenges.


D.

Track system usage and report user activity.


E.

Log the issue in the project risk register.


F.

Create a memorandum of acceptable use.


Expert Solution
Questions # 46:

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

Options:

A.

RFP


B.

WBS


C.

SLA


D.

SOW


Expert Solution
Questions # 47:

Which of the following is a quantitative key performance indicator?

Options:

A.

The project sponsor ranked the graphics of an application as four out of five.


B.

The project implements the application in ten different geographical regions.


C.

The workers complete tasks on average 25% faster using a new application.


D.

The use of a multimedia interface appeals more to users under the age of 21.


Expert Solution
Questions # 48:

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Options:

A.

Some work packages are missing from the WBS.


B.

Information is missing from the RACI matrix.


C.

New knowledge bases were introduced.


D.

Team touch points are missing.


Expert Solution
Questions # 49:

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

Options:

A.

Rollback plan


B.

Downtime stage


C.

Maintenance window


D.

Validation checks


Expert Solution
Questions # 50:

A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?

Options:

A.

Establish communication channels


B.

Plan a kickoff meeting


C.

Develop a responsibility assignment matrix


D.

Identify the stakeholders


Expert Solution
Viewing page 5 out of 14 pages
Viewing questions 41-50 out of questions