Pass the CompTIA Project+ PK0-005 Questions and answers with CertsForce

Viewing page 5 out of 12 pages
Viewing questions 41-50 out of questions
Questions # 41:

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

Options:

A.

Performance testing


B.

User acceptance testing


C.

Stress testing


D.

Unit testing


Expert Solution
Questions # 42:

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options:

A.

Ask a developer to create a change request.


B.

Do nothing because recommendation is scope creep.


C.

Ask a developer to implement the recommendation.


D.

Communicate the change status.


Expert Solution
Questions # 43:

Which of the following is the best example of CapEx?

Options:

A.

Taxes


B.

Vehicles


C.

Salaries


D.

Utilities


Expert Solution
Questions # 44:

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options:

A.

Update the work breakdown structure.


B.

Review the backlog.


C.

Seek baseline approval.


D.

Establish the resource pool.


Expert Solution
Questions # 45:

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

Options:

A.

Reassigning resources


B.

Removing access


C.

Closing contracts


D.

Evaluating the project


Expert Solution
Questions # 46:

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

Options:

A.

To move the system to a production environment


B.

To obtain project sign-off


C.

To formalize the end of the contract


D.

To release resources


Expert Solution
Questions # 47:

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

Options:

A.

Memorandum of understanding


B.

Request for information


C.

Statement of work


D.

Non-disclosure agreement


Expert Solution
Questions # 48:

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding


B.

Smoothing


C.

Forcing


D.

Compromising


Expert Solution
Questions # 49:

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

Options:

A.

Quote


B.

Information


C.

Proposal


D.

Bid


Expert Solution
Questions # 50:

During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

Options:

A.

Escalate the issue with the project sponsor and ask for assistance in managing the situation.


B.

Work with the vendor to achieve a compromise that benefits everyone.


C.

Approve the invoice to avoid damaging the relationship with the vendor.


D.

Schedule a call with the vendor PM and vendor executive to review the statement of work.


Expert Solution
Viewing page 5 out of 12 pages
Viewing questions 41-50 out of questions