Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the CompTIA Project+ PK0-005 Questions and answers with CertsForce

Viewing page 5 out of 14 pages
Viewing questions 41-50 out of questions
Questions # 41:

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

Options:

A.

Gantt chart


B.

Project organization chart


C.

Program Evaluation Review Technique chart


D.

Milestone chart


Expert Solution
Questions # 42:

Which of the following can a project manager infer from the following velocity chart?

Question # 42

Options:

A.

The project is on schedule.


B.

The project Is ahead of schedule.


C.

The project is behind schedule.


D.

The project is at risk.


Expert Solution
Questions # 43:

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Options:

A.

Evaluating the project


B.

Releasing the resources


C.

Closing the contracts


D.

Reconciling the budget


Expert Solution
Questions # 44:

A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?

Options:

A.

Signed contracts


B.

Archived documentation


C.

Project closeout report


D.

Lessons learned


Expert Solution
Questions # 45:

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

Options:

A.

Rollback plan


B.

Downtime stage


C.

Maintenance window


D.

Validation checks


Expert Solution
Questions # 46:

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

Options:

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.


B.

Require everyone to turn on their cameras and use the same background filter.


C.

Encourage the use of the chat and use plain language when speaking.


D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.


Expert Solution
Questions # 47:

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

Options:

A.

Exploit


B.

Share


C.

Transfer


D.

Accept


Expert Solution
Questions # 48:

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

Options:

A.

Defect log


B.

Change log


C.

Issue log


D.

Risk log


Expert Solution
Questions # 49:

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Options:

A.

Decline because it is not included in the project scope.


B.

Assess the impact of the request and create a change request


C.

Create new functional and non-functional requirements for mobile devices.


D.

Revise the baseline of the project plan by adding the new requirements.


Expert Solution
Questions # 50:

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

Options:

A.

Finish-to-start


B.

Start-to-start


C.

Finish-to-finish


D.

Start-to-finish


Expert Solution
Viewing page 5 out of 14 pages
Viewing questions 41-50 out of questions