Question #: 41
Topic #: 5

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?


A.

Gantt chart


B.

Project organization chart


C.

Program Evaluation Review Technique chart


D.

Milestone chart