CompTIA Project+ Certification (2025) PK0-005 Question # 50 Topic 6 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 50 Topic 6 Discussion

PK0-005 Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?


A.

Issue, issue


B.

Issue, risk


C.

Risk, issue


D.

Risk, risk


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.