During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?
A.
Hold a new backlog prioritization meeting.
B.
Add milestones to check the project's progress.
C.
Adjust the task relationship to complete coding in advance.
Adding contingency buffers to the critical path is a method to account for potential delays, increasing project certainty. This technique is part of risk management and schedule management, as recommended by CompTIA Project+.