Questions # 51:

Which of the following is a quality assurance tool?

Options:

A.

Defining project goals


B.

Identifying the root cause analysis


C.

Assessing employee efficiency


D.

Assessing skill gaps


Expert Solution
Questions # 52:

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

Options:

A.

Time and materials contract


B.

Master service agreement


C.

Fixed-price contract


D.

Non-disclosure agreement


Expert Solution
Questions # 53:

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

Options:

A.

SOW


B.

RFI


C.

RFQ


D.

WBS


Expert Solution
Questions # 54:

Which of the following is an intended outcome of a stand-up meeting?

Options:

A.

To identify team members for next tasks


B.

To identify future tasks


C.

To identify stakeholders for next tasks


D.

To identify blocking tasks


Expert Solution
Questions # 55:

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

Options:

A.

RFP


B.

RFQ


C.

RFB


D.

RFI


Expert Solution
Questions # 56:

A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes Which of the following should the company use?

Options:

A.

Run charts


B.

Fishbone/lshikawa diagrams


C.

Scatter plot


D.

Decision tree


Expert Solution
Questions # 57:

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Question # 57

Question # 57

Select the new critical path.

Option A

Option B

Option C

Question # 57


Expert Solution
Questions # 58:

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

Options:

A.

A negative correlation exists between the number of mistakes and the working hours.


B.

No correlation exists between the number of mistakes and the working hours.


C.

A low correlation exists between the working hours and the number of mistakes.


D.

A positive correlation exists between the number of mistakes and the working hours.


Expert Solution
Questions # 59:

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.


B.

Evaluate the impact to baselines.


C.

Request another supplier to ship devices.


D.

Update the project timeline with a new project end date.


Expert Solution
Questions # 60:

Which of the following activities are performed during the closing phase? (Select three).

Options:

A.

Requesting project charter sign-off


B.

Recognizing project team efforts and rewarding team members


C.

Working with the financial team to obtain return of investment


D.

Revoking resource credentials from the system


E.

Updating the risk register with new findings


F.

Informing the functional manager about the release of resources


G.

Monitoring project team performance


Expert Solution