Questions # 51:

During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

Options:

A.

Project dashboard


B.

Gap analysis


C.

Risk register


D.

Communication plan


Expert Solution
Questions # 52:

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development


B.

Production


C.

Testing


D.

QA


Expert Solution
Questions # 53:

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000


B.

10 days and $3,200


C.

12 days and $3,800


D.

14 days and $4,000


Expert Solution
Questions # 54:

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

Question # 54

Part 2:

Question # 54


Expert Solution
Questions # 55:

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement


B.

Communication


C.

Quality assurance


D.

Risk


Expert Solution
Questions # 56:

A project manager is working on an existing, large, complex project that involves regulatory and environmental considerations. The development of a detailed project plan will be critical. Which of the following should the project manager do first?

Options:

A.

Review the project charter.


B.

Start the process of engaging the stakeholders.


C.

Arrange a kickoff meeting.


D.

Evaluate potential risks.


Expert Solution
Questions # 57:

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Options:

A.

Issue log


B.

Gantt chart


C.

Milestone chart


D.

Change control log


Expert Solution
Questions # 58:

Which of the following is part of software change control?

Options:

A.

Rollback plans


B.

Maintenance windows


C.

Validation checks


D.

Requirements definition


Expert Solution
Questions # 59:

A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).

Options:

A.

Update the issue log


B.

Create a project charter


C.

Validate the status report


D.

Monitor performance


E.

Approve deliverables


F.

Baseline the project schedule


Expert Solution
Questions # 60:

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options:

A.

Issue log


B.

Risk register


C.

Defect log


D.

Traceability matrix


Expert Solution