Question #: 56
Topic #: 6

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?


A.

RFI


B.

RFP


C.

RFQ


D.

RFB