CompTIA Project+ Certification (2025) PK0-005 Question # 59 Topic 6 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 59 Topic 6 Discussion

PK0-005 Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?


A.

Baseline


B.

RBS


C.

WBS


D.

Milestones


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.