Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2026) PK0-005 Question # 59 Topic 6 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 59 Topic 6 Discussion

PK0-005 Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

A project manager is concerned about the performance of a developer who is struggling with the new coding language. Which of the following actions should the project manager take?


A.

Send a request to the project sponsor to add an additional developer.


B.

Provide the developer with only non-critical tasks.


C.

Assign the developer training to improve the developer's skills.


D.

Remove the developer from the project team.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.