New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 59 Topic 6 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 59 Topic 6 Discussion

PK0-005 Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?


A.

Hold the project until the devices are delivered.


B.

Evaluate the impact to baselines.


C.

Request another supplier to ship devices.


D.

Update the project timeline with a new project end date.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.