PK0-005 Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?


A.

Assign a scribe to take notes.


B.

Record the meeting and transcribe the notes later.


C.

Instruct each team member to take notes.


D.

Get a facilitator for the meetings.