CompTIA Project+ Certification (2026) PK0-005 Question # 62 Topic 7 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 62 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

Which of the following best describes a program in the context of project management?


A.

It is a group of unrelated projects within an organization


B.

It is used to represent the daily activities of multiple projects


C.

It is a consolidation of related projects with a common goal


D.

It provides the definition of a project workload