Pass the CompTIA Project+ PK0-005 Questions and answers with CertsForce

Viewing page 3 out of 12 pages
Viewing questions 21-30 out of questions
Questions # 21:

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options:

A.

Resource plan


B.

Organizational chart


C.

Project charter


D.

RACI chart


Expert Solution
Questions # 22:

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Question # 22

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23


B.

5


C.

10


D.

15


Expert Solution
Questions # 23:

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

Options:

A.

Forming, storming, performing, norming, adjourning


B.

Forming, performing, storming, norming, adjourning


C.

Forming, norming, storming, performing, adjourning


D.

Forming, storming, norming, performing, adjourning


Expert Solution
Questions # 24:

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications


B.

To avoid a negative impact on other software functionalities


C.

To ensure adequate resources are in place to implement the change


D.

To confirm that the software is a business priority


Expert Solution
Questions # 25:

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

Options:

A.

Add a new risk.


B.

Perform an impact analysis.


C.

Escalate to the sponsor.


D.

Raise a change request.


Expert Solution
Questions # 26:

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB


B.

RFQ


C.

RFI


D.

RFP


Expert Solution
Questions # 27:

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

Options:

A.

Architect


B.

Project sponsor


C.

Scrum master


D.

Product owner


Expert Solution
Questions # 28:

Which of the following best describes a program in the context of project management?

Options:

A.

It is a group of unrelated projects within an organization


B.

It is used to represent the daily activities of multiple projects


C.

It is a consolidation of related projects with a common goal


D.

It provides the definition of a project workload


Expert Solution
Questions # 29:

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

Options:

A.

PRINCE2


B.

Scrum


C.

SAFe


D.

XP


Expert Solution
Questions # 30:

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

Options:

A.

Project network diagram


B.

Fishbone diagram


C.

Burndown chart


D.

Milestone chart


Expert Solution
Viewing page 3 out of 12 pages
Viewing questions 21-30 out of questions