Questions # 21:

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

Options:

A.

Implement the change.


B.

Approve the test plan.


C.

Notify customers.


D.

Develop a rollback plan.


Expert Solution
Questions # 22:

The PMO wants to streamline the routing and approval of project activities to provide up-to-date visibility of the status. Which of the following collaboration tools would be most appropriate to use?

Options:

A.

Real-time, multi-authoring tool


B.

Wiki knowledge base and search engine


C.

Workflow and e-signature platform


D.

File-sharing platform and storage system


Expert Solution
Questions # 23:

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

Options:

A.

SaaS


B.

IaaS


C.

DaaS


D.

PaaS


Expert Solution
Questions # 24:

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

Options:

A.

Performance testing


B.

User acceptance testing


C.

Stress testing


D.

Unit testing


Expert Solution
Questions # 25:

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options:

A.

Task log


B.

Cadence


C.

Milestones


D.

Work breakdown structure


Expert Solution
Questions # 26:

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options:

A.

Hold a new backlog prioritization meeting.


B.

Add milestones to check the project's progress.


C.

Adjust the task relationship to complete coding in advance.


D.

Apply contingency buffers to the critical path.


Expert Solution
Questions # 27:

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options:

A.

Critical paths


B.

Resources


C.

Milestones


D.

Work breakdown structures


Expert Solution
Questions # 28:

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

Options:

A.

Quality assurance


B.

Organizational branding restrictions


C.

State privacy acts


D.

Country legal regulations


Expert Solution
Questions # 29:

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Options:

A.

Notify customers the downtime will take longer than expected.


B.

Add new team members to help speed up validation.


C.

Begin executing the rollback plan.


D.

Record the issue and proceed with the implementation.


Expert Solution
Questions # 30:

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Question # 30

Question # 30

Select the new critical path.

Option A

Option B

Option C

Question # 30


Expert Solution