CompTIA Project+ Certification (2025) PK0-005 Question # 22 Topic 3 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 22 Topic 3 Discussion

PK0-005 Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

PK0-005 Question 22

Which of the following most likely represents the number of items in the backlog?


A.

23


B.

5


C.

10


D.

15