Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 5 Topic 1 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 5 Topic 1 Discussion

PK0-005 Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?


A.

An issue


B.

A goal


C.

A backlog item


D.

An epic


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.