CompTIA Project+ Certification (2025) PK0-005 Question # 27 Topic 3 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 27 Topic 3 Discussion

PK0-005 Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?


A.

Architect


B.

Project sponsor


C.

Scrum master


D.

Product owner