Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

CompTIA Project+ Certification (2026) PK0-005 Question # 78 Topic 8 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 78 Topic 8 Discussion

PK0-005 Exam Topic 8 Question 78 Discussion:
Question #: 78
Topic #: 8

As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?


A.

Escalate to the change control board.


B.

Update the project plan.


C.

Test the implemented change request.


D.

Communicate the change deployment.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.