New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 30 Topic 4 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 30 Topic 4 Discussion

PK0-005 Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?


A.

Project network diagram


B.

Fishbone diagram


C.

Burndown chart


D.

Milestone chart


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.