Pre-Winter Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the CompTIA Project+ PK0-005 Questions and answers with CertsForce

Viewing page 4 out of 14 pages
Viewing questions 31-40 out of questions
Questions # 31:

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile


B.

Waterfall


C.

Standard


D.

Hybrid


Expert Solution
Questions # 32:

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

Options:

A.

External


B.

Internal


C.

Mandatory


D.

Discretionary


Expert Solution
Questions # 33:

A project team is running into challenges because members are unclear about other members ' roles. Which of the following charts should the project manager create?

Options:

A.

Project plan


B.

Project road map


C.

Project milestone


D.

Project organizational


Expert Solution
Questions # 34:

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Options:

A.

The project utilized all of its available reserve.


B.

The project has scope creep.


C.

The project deviated from the critical path.


D.

The project is trending ahead of schedule.


Expert Solution
Questions # 35:

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Options:

A.

Escalate the finding to the change control board.


B.

Add a risk to the risk register for validation.


C.

Consult the RACI matrix to identify ownership of the risk.


D.

Have a meeting with the project sponsor and main stakeholders.


Expert Solution
Questions # 36:

Which of the following is a characteristic that defines a project?

Options:

A.

Will produce a profit


B.

Uses outside resources


C.

Requires a well-defined scope


D.

Has a defined start and finish


Expert Solution
Questions # 37:

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

Options:

A.

The team is working in different rooms within the same building.


B.

The team is working remotely two days per week.


C.

The team has members distributed around the world in different time zones.


D.

The team is based in the same office but has a large number of members.


Expert Solution
Questions # 38:

A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?

Options:

A.

Inform all stakeholders.


B.

Update the issue register.


C.

Follow the escalation path.


D.

Initiate a change request.


Expert Solution
Questions # 39:

A PM is working with the development team and stakeholders to determine how to relate first name, last name, and address in a database. Which of the following identifies these types of data elements?

Options:

A.

PCI


B.

PII


C.

PHI


D.

CMS


Expert Solution
Questions # 40:

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Options:

A.

Synchronous


B.

Informal


C.

Asynchronous


D.

Formal


Expert Solution
Viewing page 4 out of 14 pages
Viewing questions 31-40 out of questions