New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 39 Topic 4 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 39 Topic 4 Discussion

PK0-005 Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?


A.

Waterfall method


B.

Simulation method


C.

Precedence diagramming method


D.

Cost ratio analysis


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.