Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2026) PK0-005 Question # 39 Topic 4 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 39 Topic 4 Discussion

PK0-005 Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?


A.

Issue log


B.

Scope statement


C.

Risk report


D.

Change log


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.