CompTIA Project+ Certification (2025) PK0-005 Question # 39 Topic 4 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 39 Topic 4 Discussion

PK0-005 Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?


A.

Executing the approved contingency plan


B.

Constructing an Ishikawa diagram to determine the root cause


C.

Using a Pareto chart to prioritize the different causes


D.

Engaging the senior management team in regard to the issue


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.