Weekend Sale Special Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: CFsave75

CompTIA Project+ Certification (2026) PK0-005 Question # 38 Topic 4 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 38 Topic 4 Discussion

PK0-005 Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?


A.

Inform all stakeholders.


B.

Update the issue register.


C.

Follow the escalation path.


D.

Initiate a change request.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.