Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?
Time and materials contracts are flexible and beneficial when the project scope has many unknowns. They allow costs to be adjusted based on actual time and resources used, which is consistent with CompTIA Project+ recommendations for projects with uncertain requirements.