New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 38 Topic 4 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 38 Topic 4 Discussion

PK0-005 Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?


A.

Issue log


B.

Risk register


C.

Defect log


D.

Traceability matrix


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.