PK0-005 Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?


A.

Train the team members.


B.

Assess the resource pool.


C.

Develop a QA plan.


D.

Create RACI matrix.