Which of the following communication methods would be the most appropriate to finalize the handoff of deliverables?


A.

A virtual meeting with all the stakeholders


B.

A face-to-face kickoff meeting with the stakeholders


C.

A closure meeting with the project team and stakeholders


D.

A final report submitted via email to the stakeholders