Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

CompTIA Project+ Certification (2026) PK0-005 Question # 118 Topic 12 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 118 Topic 12 Discussion

PK0-005 Exam Topic 12 Question 118 Discussion:
Question #: 118
Topic #: 12

The project manager must create a project charter. Which of the following should be included in the charter?


A.

Project schedule


B.

Resource allocation


C.

Risk plan


D.

Stakeholder identification


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.