A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?
A backlog is commonly used in agile project management to list deliverables and tasks that have not yet been completed. It allows the project manager to prioritize and organize the workload, especially for complex projects. This aligns with agile principles as outlined in CompTIA Project+.