Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2026) PK0-005 Question # 49 Topic 5 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 49 Topic 5 Discussion

PK0-005 Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?


A.

Decline because it is not included in the project scope.


B.

Assess the impact of the request and create a change request


C.

Create new functional and non-functional requirements for mobile devices.


D.

Revise the baseline of the project plan by adding the new requirements.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.