CompTIA Project+ Certification (2025) PK0-005 Question # 77 Topic 8 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 77 Topic 8 Discussion

PK0-005 Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?


A.

Time and materials contract


B.

Master service agreement


C.

Fixed-price contract


D.

Statement of work


E.

Cost-plus agreement


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.