New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 75 Topic 8 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 75 Topic 8 Discussion

PK0-005 Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?


A.

Work with the project scheduler to update the project timeline.


B.

Communicate to the stakeholders about the updated timeline.


C.

Ask the development team to fast-track upcoming activities.


D.

Add two resources so the critical activities will finish on time.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.