PK0-005 Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?


A.

Progress reporting


B.

Meeting minutes


C.

Team touch points


D.

Change management